0111
TM 1-1740-221-13&P&P
BATTERY CABLES - (CONTINUED)
INSTALLATION
1. Secure positive battery cable terminal end to starter (WP 0034).
2. Route positive battery cable connectors.
3. Position on batteries as illustrated in (Figure 1, Item 1 and 7).
4. Tighten nuts (Figure 1, Item 6 and 10).
5. Secure negative battery cable terminal end to the transmission bell housing (WP 0043).
6. Route negative battery cable connectors.
7. Position on batteries as illustrated in (Figure 1, Item 4 and 5).
8. Tighten nuts (Figure 1, Item 9 and 10).
9. Perform Maintenance Operation Check.
10. Apply a thin coat of Petrolatum, Technical, a corrosion preventive compound, to the battery posts.
11. Close battery cover.
END OF TASK
END OF WORK PACKAGE
01113/blank