0013 00
TM 1-1730-201-13&P
REMOVAL CONTINUED
5.
Using a suitable hoist, lift the upper structure assembly (Figure 1, Item 4) from the base assembly (Figure 1,
Item 10).
INSTALLATION
1.
Position the upper structure assembly (Figure 1, Item 4) on the base assembly (Figure 1, Item 10) and secure
with the four pivot pins (Figure 1, Item 14) and eight cotter pins.
2.
Position the handrails (Figure 1, Item 7) to the base assembly (Figure 1, Item 10) and secure with the two
bolts (Figure 1, Item 8) and nuts.
3.
Fill the hydraulic reservoir (WP 0019 00, Hydraulic Reservoir).
4.
Install the hydraulic cylinder assembly (WP 0021 00, Hydraulic Cylinder Assembly).
END OF WORK PACKAGE
0013 00-2