(3) Attach green/white slings (1) through (4) to crossbar assembly with free hand as follows:
(a) Grab both sling eyes from the green/white sling (1) at the 2 oclock main rotor blade (View B) and
snap them into the corresponding sling lug located at the end of the crossbar assembly tube.
(b) Grab sling eyes from the green/white sling (2), View A, at the 4 oclock main rotor blade (View B)
and snap them into the corresponding sling lug located at the end of the crossbar assembly tube.
(c) Grab sling eyes from the green/white sling (3), View A, at the 8 oclock main rotor blade (View B)
and snap them into the corresponding sling lug located at the end of the crossbar assembly tube.
(d) Grab sling eyes from the green/white sling (4), View A, at the 10 oclock main rotor blade (View B)
and snap them into the corresponding sling lug located at the end of the crossbar assembly tube.
(4) Take one sling eye from each of the yellow/white slings (6) through (9) and snap a single sling eye
from each onto one of the four sling lugs located at the end of the crossbar assembly.
WARNING
Slowly remove hand used to balance crossbar
assembly on top of MMA, ensuring that the
green/white slings and yellow/white slings will keep
the crossbar assembly positioned on top of the MMA.
(5) Carefully lay free sling eye from each of the yellow/white slings (6) through (9) onto the helicopter for
easy access during shackle assembly hook-up in step g. of this Paragraph.
f.
Rig and install blade sleeve assemblies as follows: (Figure 3)
NOTE
Blade sleeve assemblies are attached to each main rotor
blade. An adjustable length tie-down is attached between
the sleeve assemblys top D-rings and attached to the
shackle assembly during the recovery hook-up procedure.
A fixed length tie-down is attached to the bottom D-ring of
each blade sleeve assembly and secured to a defined air-
frame point in Table 5.
(1) Orient blade sleeve assembly (Figure 3, View A) so that the markings saying TOP on both the blade
sleeve bag and straps are facing down.
(2) Fold both left and right edges of the blade sleeve bag inward until the matching loop/hook closures
are engaged.
(3) Assemble blade sleeve pole. (View B)
(4) Open bag pocket number two on the blade sleeve bag (View A) by separating the loop/hook
closures.
(5) With one hand, take hold of blade sleeve bags left side blade sleeve tab and left side blue lifting tab.
(6) With other hand, take hold of blade sleeve bags right side blade sleeve tab and right side blue lifting
tab.