TM 1-1670-260-12&P
0021 00
__________________________________________________________________________________________
DAMAGED UH-1
ONE-HOOK LONG-LINE RECOVERY PROCEDURES
__________________________________________________________________________________________
Index
Introduction................................................................................................................................................................. 1
Pre-Recovery Procedures .......................................................................................................................................... 2
Recovery Flight Parameters and Precautions............................................................................................................ 2
Components Required ............................................................................................................................................... 3
Damaged Helicopter Rigging ..................................................................................................................................... 3
Install Tail-Boom Rigging..................................................................................................................................... 3
Install Forward Main Rigging ............................................................................................................................... 5
Rig Recovery Helicopter........................................................................................................................................... 11
Hook-Up and Recovery Flight Operations................................................................................................................ 12
Post Recovery Kit Procedures ................................................................................................................................. 13
Figures
Figure 1. Damaged UH-1 and Recovery Helicopter Rigging...................................................................................... 4
Figure 2. Blade Sleeve Assembly Rigging and Installation ........................................................................................ 7
Figure 3. UH-1 Square Wedge Assembly.................................................................................................................. 8
Figure 4. Rigging Shackle Assembly.......................................................................................................................... 9
Figure 5. Typical Cargo Hook Thimble Installation (Shown in Double-Eye Configuration) ...................................... 11
Tables
Table 1. Recovery Helicopter Flight Parameters........................................................................................................ 2
Table 2. UMARK Components Required ................................................................................................................... 3
Table 3. Damaged UH-1 and Recovery Helicopter Rigging - Key to Figure 1 ........................................................... 5
__________________________________________________________________________________________
1. INTRODUCTION
This Work Package (WP) covers the rigging of a damaged (non-flyable) UH-1 using a one-hook long-line recovery
procedure, the rigging of a CH-47 or UH-60 recovery helicopter, the recovery flight, and post recovery procedures.
The long-line one-hook procedure provides for 90 feet of clearance between the recovery helicopters single cargo
hook in use and the shackle assembly that the damaged helicopter is rigged to.
Damaged Main Rotor and/or Transmission non-flyable damaged classification consist of the following:
a. Main rotor head mutilated.
b. Main rotor shaft/mast bent.
c. Main transmission cracked, broken, loose or ripped out of the airframe mounts.
(1) Engine severely damaged or ripped out (not through a structural lifting point)
d. Damaged Tail-Boom
(1) Tail-Boom cracked/broken and not suitable as a lift point.
The ground rigging crew with the Unit Maintenance Aerial Recovery Kit (UMARK) can be deployed separately or
with the recovery helicopter. The recovery process includes rigging the damaged helicopter, rigging the recovery
helicopter, hooking up the recovery helicopter to the damaged helicopter, and having the recovery helicopter
transport the damaged helicopter to a designated site.
Refer to Work Package 0001 00 for general information concerning the UMARK function and component details.
0021 00-1