Table 3. Damaged UH-60 and Recovery Helicopter Rigging Key to Figure 1
Figure 1
Item No.
Item Description
1
Green/White 150 Inches (12.5 Ft) Light Weight Sling
2
Green/White 150 Inches (12.5 Ft) Light Weight Sling
3
Green/White 150 Inches (12.5 Ft) Light Weight Sling
4
Green/White 150 Inches (12.5 Ft) Light Weight Sling
5
Shackle Assembly
6
Black/White 30 Ft Heavy Weight Sling
7
Black/White 30 Ft Heavy Weight Sling with Bridle
8
Sling Link Assembly
9
Black/White 30 Ft Heavy Weight Sling
10
Sling Link Assembly
11
Red/White 208 Inches (17.33 Ft) Light Weight Sling
12
Sling Link Assembly
13
Box Link Assembly
14
Box Link Assembly
15
Blue/White 360 Inches (30.0 Ft) Light Weight Sling
16
Black/White 30 Ft Heavy Weight Sling
17
Sling Link Assembly
18
Cargo Hook Thimble
b. Install green/white slings (1), (2), (3) and (4) as follows:
(1) Position mid-point of green/white sling (1), View A, under 2 oclock position main rotor blade retention
assembly as close to main rotor mast as possible. (View C)
(a) Ensure sling does not cross itself at any point.
(b) Bring sling eyes together.
(2) Position mid-point of green/white sling (2), View A, under 4 oclock position main rotor blade retention
assembly as close to main rotor mast as possible. (View C)
(a) Ensure sling does not cross itself at any point.
(b) Bring sling eyes together.
(3) Position mid-point of green/white sling (3), View A, under 8 oclock position main rotor blade retention
assembly as close to main rotor mast as possible. (View C)
(a) Ensure sling does not cross itself at any point.
(b) Bring sling eyes together.
(4) Position mid-point of green/white sling (4), View A, under 10 oclock position main rotor blade retention
assembly inboard of blade pitch change links and as close to main rotor mast as possible. (View C)
(a) Ensure sling does not cross itself at any point.
(b) Bring sling eyes together.
c. Carefully lay sling eyes for green/white slings (1), (2), (3), and (4) on the helicopter for easy access during the
shackle assembly hook-up in step e. of this Paragraph.
0026 00-5